Federal Ministry of Works (FMW)
... building the backbone for Development ...
Follow Us:
Welcome To Federal Ministry Of Works.
Minister Federal Ministry Of Works Engr. David Umahi.
Road Construction Inspection Tour.
Road Construction Inspection Tour.
Road Construction Inspection Tour.
Road Inspection.
Road Construction Inspection Tour.
Road Inspection.
Road Construction Inspection Tour.
Road Construction Inspection Tour.
Apr
25
2024

LATEST PRESS

FEDERAL MINISTRY OF WORKS GIVES ULTIMATUM TO CONTRACTORS HANDLING THE DUALIZATION  OF LOKOJA-BENIN ROAD,  OBAJANA  JUNCTION- BENIN IN KOGI AND EDO STATES TO SIGN THE REVIEWED CONTRACT OR FACE JOB TERMINATION

- AS HON MINISTER DIRECTS THE MINISTRY TO WITHIN 7 DAYS  AUDIT ALL  ONGOING  PROJECTS, INCLUDING PERSONNEL  AND EQUIPMENT

The Honourable Minister  of Works, His Excellency,  Sen. Engr. Dr. Nweze David Umahi CON has directed  the   contractors handling  sections I- IV of Lokoja- Benin, Obajana Junction- Benin roads in Kogi and Edo States to immediately  sign the new contract  as reviewed under the Renewed Hope administration  of  President Asiwaju Bola Ahmed Tinubu GCFR or face the termination of their job by the Federal Ministry of Works in accordance with the condition of service. 

This directive was given to the contractors  in a meeting  with the  representatives of  Mothercat  Ltd, CCECC Ltd, Dantata & Sawoe Ltd, CGC Ltd and RCC Ltd held on 25th April 2024  at the Ministry's Headquarters, Mabushi-Abuja. 

He further directed  the Ministry  to, within  7 days , carry out a comprehensive audit of the ongoing  projects with a view to  knowing  the  status of work done, the capacity  of personnel  and equipment being used by the contractors.

Speaking  during the meeting, the Honourable  Minister frowned at the pranks of the contractors who were part of the process of re-scoping and reviewing the contract specifications but failed to sign the review  contract  documents after signing that they would do the job based on the new specification. 

He said “The project was initially N121 billion, but before the administration of President Ahmed Bola Tinubu, the project was already reviewed to about over N870 billion. 

When I came in as Minister, I saw that the project was over-bloated, and I refused to take the No Objection to FEC. I had to go through the road  myself, and I realized that some sections of the road could not survive asphalt. 

So, we started meetings that took us over five months with all the contractors, and in the meetings, we agreed to re-scope the project. We re-scoped the project where we said okay, the new lanes should be done on concrete and the other ones done on asphalt. 

We kept the contracts up and we all signed the documents and based on signing the documents, we took it to BPP and from BPP we went to FEC, and before we went to FEC, we demanded for them to approve that they can do the job. 

They all gave us letters of approval.” He  wondered  why  contractors were given jobs without having the required manpower and equipment to do the job, and warned that henceforth any contractor signing a contract must sign alongside the basic rate and timeline. 

He said,” So the position of the government is that if you are not signing the contracts between today and tomorrow, you will forgo the jobs. You can go to court. We will not enter into any condition for further negotiation. 

This contract is over N2 billion per kilometer. You don't have equipment to do the work. Let me even assure you that if you are signing the contract, you will sign it alongside the basic rates. You sign it alongside the timetable, and you deploy in three sections, or I will terminate the job. Enough of playing with the psyche of the people." 

He further stated that the Ministry would  not allow  any contractor  to hold the country to ransom or to impose their conditions  on the Ministry. "You don't want to work, leave the job. It's not compulsory that you must be the one to do the job. You cannot be on site, and the people are dying. The vehicles are falling down, and you're playing politics with the lives of the people. And we fold our hands and leave you for what? You can't be on site....So if you are not working, pack your things out of that site."

In his remarks,  the Director,  Highways (SP) South, Engr. C.A Ogbuagu  gave account  of  the  technical processes undertaken by the Ministry before  Federal  Executive Council approved the  augmentation of the  project,  which the contractors accepted,  and letters of award were given to them. He wondered why the contractors refused  to sign the new document.

He said," After the FEC's approval of the argumentation, the legal department was brought in so that this new contract will now be executed so that work will continue on site. So, for about two weeks now, the draft addendum has been with the contractors, and none of them has positively responded, except  RCC."

The CGC in his reply, expressed commitment to the directive of the Hon. Minister and said, "for our side, and firstly for our section, and currently we are seriously working. 

And secondly, we have a sent the draft to the Head Office And there is any issue, we have answered them and may be later tomorrow morning, we can get the approval from them so we can go ahead."  It is hoped that the other contractors will sign the new contract latest Monday 29th April, 2024. and mobilize effectively to the site.
 

Apr
24
2024

BODO-BONNY ROAD:  FG ORDERS JULIUS BERGER TO RETURN TO SITE WITHIN 14 DAYS OR FACE SANCTIONS The Federal government has ordered the contractor handling the Bodo- Bonny road construction to return to site within 14 days or risk appropriate sanctions. Works Minister, His Excellency, Distinguished Sen. Engr. (Dr) David  Umahi gave the marching order today at a meeting with the handlers of the road project, Julius Berger  PLC , as well as representatives of Nigeria Liquefied Natural Gas NLNG and Royal Fathers from Bonny Kingdom  and  other members of host  communities in Abuja. According to the Minister, the Bonny-Bodo road contract which was initially awarded at the cost of N120 billion in 2015, was later varied at N199 billion with a completion dateline of December 2023, which has since elapsed. The Minister deplored the unilateral stoppage of work by Julius’ Berger, describing the action as unacceptable. While rejecting in total, Julius Berger’s request for variation based on fluctuations in exchange rate and increasing cost of material, the Minister said government does not award contract based on exchange rate. He pointed out that no contractor will come to government for a downward review of the cost of any project if the exchange rate becomes one naira to one dollar, adding that government cannot anchor contract cost based on exchange rates variations. Senator Umahi was particularly unhappy that the timelines for the completion of the project were not adhered to, maintaining that if the project were  completed in December 2023,   as contained in the contract agreement , issues  of high exchange rate and increasing cost of materials would not have arisen ‘ He however promised that he would make a presentation to Mr President and commander in Chief His Excellency Bola Ahmed Tinubu for a marginal augmentation to ensure that the project is completed on or before December 2024, particularly in the Spirit of the Renewed Hope Agenda and the love President Tinubu has for Bonny Kingdom and other host communities in the Niger Delta Region. Earlier in his presentation, the Managing Director, Julius Berger Plc    Engr Dr. Lars Richter called for the variation of the contract which he said has become necessary in view of the declining value of  the Naira and rising cost of construction materials in the country. The Managing Director drew the attention of the Minister to the time lag when the contract was awarded in 2015 when the exchange rate was N305 to a dollar, adding that the cost of building materials has since risen by over 1000%. Contributing, the Deputy Managing Director of NLNG, Olakunle Osobu pointed out that the contract which is being funded through the Tax Credit Scheme is intended to complement the Renewed Hope Agenda of the current administration, calling on all parties to the project to remain patriotic as well as make the necessary sacrifices for the actualisation of the project.     On their part, Roya Fathers of Host Communities led by Chief Abel Attoni, Palace Secretary, Bonny Kingdom expressed profound gratitude to President Bola Ahmed Tinubu over the decision of the Renewed Hope administration to ensure that Bodo-Bonny road is completed. His Royal majesty applauded the commitment of the Works Minister to the road project especially coming at a time the Nation is experiencing economic difficulties. ...

Apr
23
2024

Those Criticizing the Ongoing Lagos- Calabar Coastal Highway Project Being  Done by  The Renewed Hope Administration Of President Asiwaju Bola Ahmed Tinubu  Either Have Little Knowledge of the Concept of EPC+F On Project Financing Or  Are Deliberately Sacrificing The Cause Of  Development  At The Altar Of Politics The trending posts of   criticisms by some notable  politicians on the propriety and priority of the Lagos-Calabar coastal highway project being executed  by the Renewed  Hope administration  of His Excellency President Asiwaju Bola Ahmed Tinubu GCFR are no doubt baseless thoughts of critics who are either bereft of the knowledge of the workings of the project  initiative or they deliberately  want to sacrifice the modest developmental efforts  of Mr. President  at the altar of  their political ambitions. It is unthinkable  that such highly  placed people fail to understand  the various  elucidations provided  by the Honourable Minister  of Works,  His Excellency,  Sen Engr Nweze David Umahi CON  on when the project  was conceptualized, the various  administrations that attempted   but failed to carry out the project, the economic  and technical  considerations that gave rise to the commencement  of the project under the Renewed Hope administration, the funding  and procurement details  and indeed the dimensions, importance, priority and propriety of the projects  in the national developmental trajectory. For the avoidance  of doubt,  the Lagos- Calabar coastal highway  project is being done under EPC +F. What does this type of funding  entail? This is a project financing mechanism in which EPC+F contractors also arrange financing for the project. EPC+F is Engineering, Procurement  and Construction plus Financing. Engineering  here includes design and specification. This initiative provides  a fixed  price, fixed date, and transfers risks to the contractor. This type of funding requires only a counter- part funding  from the Federal Government. Such funds  are sourced  by contractors where they have confidence  in the  economic policies of government, which essentially entails  allowing  the participation of the private  sector  in the road infrastructure  development through  PPP or EPC+F.   In the recent  Inauguration  of the Committee  on Compensation  of owners of properties that will be affected  by section 1 of the Lagos- Calabar Coastal Highway, the Honourable Minister emphasized the nature of the project funding  and the workings of EPC + F when he said, "And graciously, Mr. President had approved that this section three will start from Calabar, which is the end point of the project, and start running towards Akwa Ibom. So, the 700 km is procured  under phase one, in phases, and it's EPC +F. EPC+F is engineering, procurement, construction, and finance. And so, under this kind of arrangement, the contractor is expected to bring in a certain amount of money, and Federal Government is expected to pay certain counterpart funding." No patriotic  Nigerian  should discourage  this kind of project  where funding is substantially  from the contractor. There is no doubt  that Mr. President  is aggressively  tackling  the backlogs  of uncompleted  road projects. In the 2023  Supplementary Budget,  Mr. President  approved funds for intervention on the over 260 dilapidated roads nationwide.  The 2024 appropriation  made provision for capital  investment  on our critical  roads across  the 6 Geo- political  zones of Nigeria. The Honourable Minister  has already  made a great difference  in the road infrastructure development  roadmap of this administration through his new innovations on road construction  and rehabilitation, his power of supervision, and his contract negotiation power which  is second  to none in the history  of the Federal Ministry of Works. He has been touring around and supervising   the various  ongoing  projects  of the  federal government, and the difference  is already  there. The people  are testifying of the quality  and speed of road projects being  executed by the Renewed Hope administration. He has proven track records on road  infrastructure development.  He is not into rhetorics like many politicians who talk high but can do only less. The administration of President  Tinubu  is doing roads that will stand the test of time. The  roads he is fixing  will  facilitate economic  recovery.  The patriotic  Nigerians are already  applauding  the good efforts of Mr. Presidentt, but professional  politicians  are busy criticizing  a landmark  project  that will launch Nigeria into the league  of the best economies of the continent.  On the importance  of the Lagos-Calabar coastal highway project  to the economy  of the  nation, it is clear that the coastal highway, when completed, will foster national economic growth. Notably,  all roads in the country are  important as reflected by the interventions of this administration on road rehabilitation across the nation, but the coastal highway offers much more economic benefits to the nation because  of its connectivity  to the North  and South through  the existing spurs. The road, when completed, has the potential to increase Nigeria’s GDP and trigger industrialisation, create trade, enhance the  transportation  of goods and services, and  safety of road users.The road is going to be the biggest super highway in Africa in terms of the structure and solidity as we all as utility value, having ten lanes with a rail track designed for concrete technology, covering 700 kilometers. It is going to attract foreign direct  investment to Nigeria, and it is going to trigger economic development. It is going to develop the potential of our coastal businesses, especially  at the local economic corridors, and boost tourism and marine businesses.  ...

Apr
19
2024

Lagos- Calabar Coastal Highway: A Renowned Policy Analyst Describes Cost of Project as One of The Most Effective Project Figures in The World, Says Sen. Umahi's Negotiation Power is Second to None Blueprint Newspaper Written By Bode Olagoke A think tank body of policy analysts on the platform of the Independent Media and Policy Initiative (IMPI) Wednesday justified the N2.8trn to be expended on the construction of the Lagos-Calabar coastal highway. The group said the cost of construction of the highway "is appropriate." It also faulted former Vice President Atiku Abubakar's criticism of the project, saying there is enough proof to support the cost of the mega project. IMPI in a statement by its chairman, Niyi Akinsiju, in Abuja Wednesday said its study of the situation shows that all the claims by the Peoples Democratic Party (PDP) presidential candidate were off the mark and targeted at discrediting the project. The think tank group acknowledged the track record of the project handling firm in constructing coastal highways with reinforced concrete in many countries, citing the successful handling of the Bar Beach Shoreline protection. On Atiku's criticism of the cost of the project, the policy group insisted that a cost analysis of road projects similar to the Lagos-Calabar highway in some parts of the world show that the cost of the project was appropriate. The statement reads: "We note that there is no unified standard pricing template for the cost of building a kilometre of road anywhere in the world. The realities of road building have much to do with several variables: location, train, type of construction, number of terrain, lanes, lane width, surface durability, and the number of bridges, to name a few. "Yet, for engagement, we reviewed some cost estimates in some other countries to establish the context of fraud or otherwise that Waziri Abubakar is trying to throw up. "To build a 2-lane road of 12 metres wide of each lane with no bridges in states of North Eastern United States of America is $3.34m per km (when converted to Naira using the N1200/$ adopted by Umahi, it comes to N4.08bn per km) while the same 2-lane road in South Eastern USA with no bridges is $ 3.78m per km (N4.53bn per km) "According to the Texas Department of Transportation, the average cost of building a concrete road in rural areas is around $2.5m per mile, while in urban areas, it can costs upwards of $5m per mile. "In California, the estimated cost of building a concrete road ranges from $3 million to $6 million per mile, depending on the location and other factors. In Australia, average road project costs were around $5.1m (N6.12bn) per lane kilometre in 2017. "But in Bangladesh, according to the World Bank, the estimated cost of construction is $6.6m (N7.92bn) per kilometre for the Rangpur-Hatikumrul highway, $7m (N8.4bn) per kilometre for Dhaka-Sylhet highway, $11.9 million (N14.28 billion) per kilometre for Dhaka-Mawa highway. This underscores cost differentials in road construction because of peculiarities in terrains."   ...

First First

PUBLIC ANNOUNCEMENT


Apr
19
2024

 


OTHER NEWS

Feb
19
2024

Meeting of Cement Manufacturers – Dangote Cement Plc, BUA Cement Plc, Larfarge Africa Plc & Cement Producers Association with the Honourable Minister of Industry, Trade & Investment, Dr. Doris Uzoka-Anite and the Honourable Minister of Works, Sen. Engr. Nweze David Umahi, CON held at the Office of the Honourable Minister of Works, Mabushi, Abuja on Monday, 19th February, 2024


1. The meeting noted the challenges of the manufacturers like:
    a.    Cost of gas;
    b.    High import duty on spare parts;
    c.    Bad road network;
    d.    High foreign exchange; and
    e.    Smuggling of cement to neighbouring nations.

2.    The government noted the challenges and reacted as follows:
a.    Federal Ministry of Industry, Trade and Investment to seek some remedies from Mr. President on cost of gas and import duties.

b.    Federal Ministry of Works to give more attention to fixing of the roads, especially around the locations of the manufacturers.

c.    On the issue of smuggling cement, the Federal Ministry of Industry, Trade and Investment to deepen the already started engagement with the National Security Adviser on how to stop the smuggling.

3.     The cement manufacturers and the Government noted that the current high price of cement is abnormal in some locations nationwide.  Ideally, cement retail prices should not cost more than ₦7,000.00 to ₦8,000.00/ 50kg bag of cement.  Therefore, the three cement manufacturers: Dangote Cement Plc, BUA Cement Plc and Larfarge Africa Plc have agreed that cement cost will not be more than between ₦7,000.00 and ₦8,000.00/50kg bag depending on the location.

4.    Going forward, Government advised cement manufacturers to set up a price monitoring mechanism to ensure compliance, and manufacturers have willingly accepted to do so and to sanction any of her distributors or retailers found wanting.

5.    Government expects the agreed price to drop after securing government's interventions on the challenges of the manufacturers on gas, import duty, smuggling, and better road network.

6.    The meeting agreed to reconvene in 30 days to review progress made.

SPEECHES

Dec
12
2023

Brief by the Honourable Minister of Works, Senator. (Engr) Nweze David Umahi CON, FNSE, FNATE on the Occasion of the Presentation and Defence of the Ministry’s 2024 Budget io the Joint Committee on Works

 

The Chairman,
Senate Committee on Works,
Distinguished Senators,
The Chairman,
House Committee on Works
Honourable Members

 

1.0    INTRODUCTORY REMARKS
I wish to express the appreciation of the Ministry to the Joint National Assembly Committee on Works for this opportunity to present and defend the Ministry’s 2023 Budget Performance and 2024 Budget Proposal. The Ministry received the letter Ref. No. NASS/S&H/COW/01/10/1 dated 30th November, 2023 from the Joint Committee on Works requesting for details and submissions on issues pertaining to the performance of the 2023 Appropriation and 2024 Budget proposal. These documents have also been earlier submitted in response to the said letter. I will also like to explain and highlight some aspects of the submissions in the course of this budget defense.

 

2.0    OVERVIEW OF THE 2023 APPROPRIATION
The sum of N534, 455,695,989.00 was appropriated to the Ministry of Works and Housing and its Parastatals in the 2023 fiscal year. From this amount, Works and Housing Sectors of the then Ministry was allocated a total Capital of N453,255,980,966.00. Following the demerger of the Ministry, Federal Ministry of Works was allocated the sum of N383, 351,656,449.00 as Capital, Overhead was in the Sum of N525,362,343.96 and Personnel was in the Sum of N6,916,751,203.00. The details of the Appropriation are as follows:

(a)     Capital Allocation:                
i. Main Ministry of Works:                 N383,351,656,449.00
ii. Parastatals:                                 N 46,215,578,221.00
Total                                               N429,567, 234, 670.00

 

(b)    Overhead Cost:                            
i. Main Ministry:                     N535,362,344.40
ii. Parastatals:                    
a. Office of the Survey-General of the Federation (OSGOF)         N239, 664,804.00
b. Federal School of Surveys (FSS), Oyo                                  N50, 523,550.00
c. Federal Roads Maintenance Agency (FERMA)                      N17, 525,286,292.00
d. Council for the Regulation of Engineering in Nigeria (COREN) N9, 691,801.00
e. Surveyors’ Registration Council of Nigeria (SURCON)             N14, 971,301.00
    Total                                                                                  N18,375,500,092.4

 

(c)    PERSONNEL COST
i.    Main Ministry                            N6,916,751,203.00
ii.   Parastatals                               N5,234,644,736.00                      

Total                                              N12,151,395,939.0


3.0    2023 BUDGET RELEASES/PERFORMANCE

 

As earlier said, the Capital Allocation to the Ministry was N383, 351,656,449.00 after the demerger of Federal Ministry of Works and Housing. The releases so far to the Ministry was in the sum of N184,165,147,332.29, which represents 48.01% of the Capital Allocation in the 2023 Appropriation. This leaves a balance of N199, 405,010,166.71 to be released by the Federal Ministry of Finance (FMF).

 

3.10.    Capital Projects


The sum of N184,165,147,332.29 released up to date to the Ministry from the 2023 Budget Appropriation had been utilized for payments of some certified Certificates for executed works on roads and bridges by Highway, projects of Engineering Services and Common Services Departments.  It is to be noted that as at the end of November 2023 the Ministry had a cumulative unpaid certificate in the sum of N1,507,873,365,516.02 (One Trillion, Five Hundred and Seven Billion, Eight Hundred and Seventy-three Million, Three Hundred and Sixty-five Thousand, Five Hundred and Sixteen Naira, Two Kobo) only for all inherited on-going highway and bridge projects. Apart from the pressure on the resources to pay, there is the inadequacy of annual budgetary provisions where in most cases N100m or N200m and even less was provided for projects estimated to cost above twenty- fifty billion Naira or even more. Awarding such projects even though appropriated is difficult on its own because the provision is inadequate to even pay 10% for mobilization whereas the Procurement Act prescribes 30% mobilization. The details of all the 2023 Budget Performance for Highways Capital Projects are provided in the document attached as Annexure I.

 

3.20    Overhead   

Out of the Total Approved Overhead of N535,362,344.40 the sum of N312,294,700.90 was released to the Ministry for overhead costs for the period January - July, 2023, which represents 58.33% of the budgetary provision with an outstanding sum of N 223,067,643.50.

 

3.30    Personnel Cost


The Personnel Cost of N12,598,351,319.00 for the Ministry is being implemented through the Integrated Payroll and Personnel Information System (IPPIS) programme in the Office of the Accountant-General of the Federation.

 

4.0    REVENUE GENERATED

The sum of N723,063,678.62 was generated as revenue from January to November, 2023 and all the revenue realized have been remitted to the consolidated Revenue Account (evidence of IGR remittance enclosed).

 

5.0    2024 BUDGET PROPOSAL
The total sum of N 657,228,251,596 was proposed for the Federal Ministry of Works and its Parastatals for Capital, Personnel and Overhead estimates in the 2024 Appropriation Bill. The breakdown of the proposals is as follows:

 

5.10    Capital Budget Proposal            
a). Main Ministry of Works                                       N 566,466,977,361
b). Parastatals    
i. Federal Road Maintenance Agency(FERMA).         N 51, 282,456,911               
ii. African Regional Institute for Geo-Spacial Information Science and Technology AFRIGIST (RECTAS) N 104,039,920
  Grand Total                                                           N 617,853,474,192

 

5.20 Overhead Budget Proposal                
a). Main Ministry of Works                           N 668,116,856.00
b). Parastatals:
i. FERMA                                                   N 22,027,209,696.
ii. RECTAS/AFRIGIST                                 NIL                          
          Grand Total                                      N 22,695,326,552

 

5.30 Personnel Cost Proposal            
i. Main Ministry of Works                          N 12,598,351,319
ii. Parastatals                                          N 4,081,099,533
             Grand Total                                N 16,679,450,852

 

Please note that without any presidential pronouncement, the following Parastatals which have been under the Ministry of Works have been provided for in the Budget Proposal for the Ministry of Housing and Urban Development as follows:
i.    Office of the Surveyor-General of the Federation (OSGoF);
ii.    Federal School of Surveying, Oyo (FSS);
iii.    Council for the Regulation of Engineering in Nigeria (COREN); and
iv.    Surveyors’ Council of Nigeria (SURCON)
It will be good that these Committees do get these Parastatals back to the Federal Ministry of Works.    

 

6.0     CATEGORIZATION OF ONGOING HIGHWAY PROJECTS UP TO 2023

The Ministry undertook a total of 2,097of on-going/inherited projects at a total Contract Sum of N13,835,640,624,786. The total amount certified to date stood at N4,772,770,148,140.41, while the total amount paid was in the sum of N3,140,569,453,163,82 as at November, 2023. 3 details are shown in Annex I.

 

Some of the projects are categorized according to special funding mechanism as follows:


6.10    Highway Project Financed with Presidential Infrastructure Development FUND (PIDF).
A total of Four selected critical projects are being funded under the Presidential Infrastructure Development Fund (PIDF) Project which is managed by the Nigerian Sovereign Investment Authority (NSIA).  The projects are:
a.    Expansion and upgrading of Lagos-Ibadan Expressway Section I (Lagos-Shagamu);
b.    Expansion and upgrading of Lagos-Ibadan Expressway Section II (Shagamu-Ibadan);
c.     Reconstruction/Rehabilitation of Abuja-Kaduna-Kano Road; and
d.     Construction of 2nd Niger Bridge and two Bypasses at Asaba and Onitsha.

 

As at date, the total sum of N846, 365,489,635.12 has been certified out of the initial projects cost N1,535,375,595,518.43. This translates to a performance of 55.12%. The Lagos-Ibadan Expressway has been substantially completed to about 90% but we still lack fund to complete the project. The Abuja-Kaduna-Kano Road is in three sections with about 127km uncompleted in section I (Abuja-Kaduna). Section II which is Kaduna-Zaria is fully completed and section III which is Zaria-Kano is on-going with 20km left uncompleted. The total cost of the three sections is about N655billion. The contractor is seeking for a review of contract to about N1.37trillion to complete the project. We are reviewing the request. However, even though the project will not get up to N1trillion when fairly reviewed, we believe that the unit rates ought to be reviewed. For example, the subsisting unit rate of Asphalt on the project is about N11,000 per square meter, whereas the real cost now is not less than N20,000 per square meter. We have requested the contractor to execute the first 40km of section I on concrete. It is important to note that we do not have fund to continue the project by February 2024 if no funding is injected into the project.

 

The 2nd Niger Bridge has been completed and was recently handed over to the Ministry. Additionally, there remains the construction of the Approach roads 2A and 2B which were awarded by FEC but have funding challenges to take-off.  The remaining two Bypasses in Asaba (2A) and Onitsha (2B) awarded to Julius Berger Nigeria Plc and Reynods Construction Company Nigeria Limited respectively, during the last Administration was initially estimated at about N200billion but now with inflation, the cost may be up to N260billion. There is no funding for these projects and the projects have not taken off. Let me note that without these Bypasses, the completed 2nd Niger Bridge will be almost inoperative. The details of these projects are as shown in Annexure II.

 

6.20    Highway Projects Financed with the Sovereign SUKUK Fund
The Federal Government through the Debt Management Office (DMO) initiated Sukuk Funding Programme for financing road infrastructure in 2017. The total sum of N683.122bn was raised to fund 25, 28, 44, 71 and 63 number projects in years 2017, 2018, 2020, 2021 and 2022 respectively. All the works milestones for the Sukuk in year 2017, 2018, 2020 and 2021 were completely drawn down while the 2022 Sukuk, issued in the sum of N110,000,000,000.00 is on-going. A total of 63 selected critical projects are being funded under the 2022 Sovereign Sukuk Issuance. As at end of November 2023, the total sum of N50,537,288,079.45 was drawn down translating to a performance of 46%. The details of execution of the projects and drawdown of the 2022 Sukuk Bond is as shown on Annex III;

 

6.30    The Nigerian National Petroleum Company Limited (NNPC) Funded Projects Phase I
The NNPC joined the Road Infrastructure Development & Refurbishment Tax Credit Scheme programme by undertaking to finance 21 roads in the sum of N621bn with total length of roads of about 1,804.6km under the NNPC Phase I. These roads were identified by key stakeholders such as the NNPC, Petroleum Tanker Drivers Association (PTD) and the Ministry etc. as being crucial for the efficient distribution of petroleum products across the nation. As at date, the total drawdown forwarded to the NNPC Limited is in the sum of N247,729,252,899.54 out of the Federal Executive Council (FEC) approved sum of N621,237,164,794.59 representing 39.88% performance. The funding gap here due to inflation is estimated at over 250bn. The details of NNPC Phase I Funded Projects are attached as Annex IVA;

 

6.40    The Nigerian National Petroleum Company Limited (NNPC) Funded Projects Phase II
The NNPC Phase II Funded Projects were approved by the Federal Executive Council in the sum of N1,969,700,168,910.78 for the execution of 44 No. roads with total length of 4,554.19km while the initial Contract Sum was about N3.969trillion. This leaves a funding gap of over N2trillion at the time of starting the projects. Presently, with inflation, the funding gap to have the NNPC Phases I & II completed shall stand at about N3.56trillion (Inflation about N1.5trillion) for two years from now. This funding gap is neither appropriated for nor has any source of funding. This means that without the kind intervention of this Distinguished and Honourable Joint Committees of Works, these projects will not go on mostly from March 2024 when the NNPC funding would have been exhausted. Your kind intervention and advice are highly, highly and urgently solicited. As at date, the total drawdown forwarded to the NNPC Limited is in the sum of N752,093,618,603.51 representing 38.18% performance. The level of drawdown seems low because most of the projects needed to be reviewed due to the inflation, The details of NNPC Phase II Funded Projects are attached as Annex IVB.

 

6.50 Other projects funded under Road Infrastructure   Development & Refurbishment Tax Credit Scheme.
Several Companies have leveraged on the Executive Order No.7 of 2019 to commit investments in the construction/rehabilitation of roads and obtain Tax credit. Companies like NLNG Limited, Dangote Industries Limited, BUA International Limited, MTN Nigeria Communications Plc, Mainstream Energy Solutions Limited and GZI Industries projects have embraced the Road Infrastructure Development & Refurbishment Tax Credit Scheme program. Twenty-one projects at a total cost of N1.338trillion outside of those being funded by the NNPCL are being executed under this Scheme. The details are attached as Annex IVC; and
a)    Projects funded from Multi – Lateral Loans.
4Nos. major highway and bridge projects are being funded through Multilateral Loans and grants from the African Development Bank (AfDB) and the China Exim Bank. The details of these projects are attached as Annex V.

 

7.0   2023 APPROPRIATION OF ALL ONGOING EMERGENCY/SPECIAL REPAIRS AND LIMITED REHABILITATION PROJECTS

These are projects being executed under emergency repairs works along the Federal Highway network. The projects under this category have a total contract cost of N419,841,989,869.00, with a total amount certified in the sum of N307,486,496,856.58, while the total amount paid is in the sum of N 123,213,264,774.77, the Ministry is indebted to Contractors to the tune of N 184,273,232,081.81. The details of these projects are included in Annex I.

 

8.0    INTERVENTION ON TERTIARY INSTITUTIONS PROJECTS  
These are projects being executed under the intervention in Federal Government Tertiary Institutions. Out of 108 projects under this category at a total contract cost of N15,641,954,804.16, 61 projects have been completed and handed over at a total cost of N10,790,866,435.35 as at end of November 2023. Twenty-one projects at a total cost of N3,874,482,841.53 have been completed awaiting handover, while the remaining 26 at a total cost of N3,491,998,752.77 are on-going. The details of these projects are attached as Annex VII.

 

9.0    OVERGROWN VEGETATION CONTROL PROJECTS  
These are projects being executed under the intervention on Federal Government Tertiary Institutions. The projects under this category have a total contract cost of N2,333,448,750.00, with a total amount certified in the sum of N1,795,927,968.71, while the total amount paid is in the sum of N62,060,468.75, the Ministry is indebted to Contractors to the tune of N1,733,867,499.96. The details of these projects are included in Annex I.

 

10.0 PROJECTS PRIORITIZED FOR COMPLETION 2022-2024
In spite of all odds, 21 major road and bridge projects have been completed and some were commissioned, while others are ready for commissioning. The total cost of the completed major road and bridge projects is in the sum of N498,802,362,642.46 with a total length of    489. 97km.  Also, to be completed in 2024 is the 260 Emergency Repair works in the 2023 Supplementary Appropriation at a total cost of about N260bn. The detail of completed projects is attached as Annex VI.

 

11.0 BRIDGE CONSTRUCTION/ REHABILITION PROJECTS
Under the 2023 budget, the Ministry undertook massive rehabilitation of bridge projects, some of which have never been maintained since they were constructed over 50 years ago. Human activities on these bridges (i.e. vandalization, fire incidents) have left these bridges in deplorable state and unserviceable conditions. The Ministry is trying to sustain these critical works in the 2024 budget as well as undertake the construction of new bridges where there was none in order to reduce travel time as well as the reconstruction of bridges to replace collapsed ones.

 

These projects are:
a).    Comprehensive Repairs of the damaged elements of the Third Mainland bridge superstructure: This was procured this year and works are currently ongoing and is satisfactory so far. The second Phase which involves the substructure repairs is being processed for award.
b).    Comprehensive emergency repairs of Eko and Marine bridges in Lagos State: Works are ongoing on these bridges. The Contractor has attained appreciable progress and is being supported financially to enable expeditious completion due to the emergency nature of the works.
c).    Proposed Rehabilitation of Carter, Iddo, Liverpool and Iganmu bridges in Lagos State: The present condition of the above bridges calls for urgent rehabilitation works to restore the bridge integrity and forestall further deterioration that may be detrimental to road users. In this regard, the procurement process is already ongoing within the Ministry for the emergency award of contract for the repairs/rehabilitation of these bridges.
d).    The Rehabilitation of Jimeta bridge in Adamawa State and Murtala Mohammed bridge at Koton Karfe along Lokoja – Abuja Road; Works on these bridges are ongoing and will soon be completed.
e).    Proposed construction of Shendam bridge in Plateau State, Reconstruction of failed bridges in Enugu State and the Construction of Buruku bridge in Benue State; and
f). Reconstruction of three failed Bridges on East/West Road

 

These are new bridges that are required to ameliorate the sufferings of the host communities as well as other commuters. Procurement of contract for the construction of these bridges are already at an advanced stage and will soon be completed. Funds will be needed to bring them into reality.

 

12.0    NEW PROJECTS IN 2024 BUDGET  
There are new projects captured under the 2024 Budget at a total cost of N102,956,624,538.00. See Annexure 13

 

13.0    PROSPECTS AND PROSPECTS OF THE 2024 BUDGET FOR HIGHWAY PROJECTS

The policy thrust regarding the 2024 budget for highway projects is to ensure completion of some critical on-going projects which have attained significant levels of completion while keeping the rest alive through minimal appropriation. 693 new projects have been proposed in the 2024 budget, which are critical to improving road network connectivity and thus enhancing traffic circulation on the Federal Road network, necessary for boosting socio-economic activities in the country. The primary objective is enabling the Ministry achieve its mandate in providing a quality Federal Road network that serves as an environment to aid socio-economic growth of the country.

 

The main challenge to highways development in the Country remains inadequate funding. As at date, Government is committed to highway contractors to the tune of about N13.835 trillion with a total of about N1,507,873,365,516.02 unpaid certificates for executed works. Secondly, the dearth of younger Engineers/Technical Officers in the Ministry as a result of embargo on employment is affecting effective project supervision at the sites. It is expected that more sources of funding of highway projects be explored as well as lifting the embargo on employment of needed Engineers/Technical officers at middle level to enhance supervision of projects. Our Ministry has set up six committees to review all debts, approved and unapproved variations on prices of basic rates, and all augmentations that occurred before May 29th 2023 and from May 30th 2023 till date.

 

14.0    RECOMMENDATIONS
14.10 From the fore-going, I would like to recommend as follows:
a)    The provision of an Emergency Fund of about 30% of the Budget Provision to cater for unforeseen emergencies that regularly occur on the road network especially during the rainy seasons;
b)    An increase of the Ministry’s present budgetary allocation to about N1.5tr to complete at least 10 selected critical roads and bridges in each of the six geo-political zones of the country;
c)    Urgent review of all certified debts to contractors and if possible, convert same to Promissory Notes to contractors so that we can get properly focused in using any fund appropriated to us to pursue the Ministry’s set objectives;
d)    Inflation- Many contractors are presently out of sites because they have exhausted their contract VoPs and needed the projects unit rates to be reviewed. It will be good that all VoPs and augmentations of all the projects are reviewed and those that are owed be converted to Promissory Notes, while unit rates regime will take effect on contractors in line with the current realities of the construction industry.
e)    More eligible companies should be encouraged to key into the Road Tax Credit Scheme to increase the number of private sector interventions. This means front-loading their tax liabilities to solve our present challenges;
f)    Raising of Bonds from the Capital Market to finance road development in the country;
g)    Creation of an enabling environment by fixing the roads so that the deployment of the Highway Development and Management Initiative (HDMI) can be effective; and
h)    That appropriations for projects be such that no projects when started should last for more than four years.

 

14.20     ISSUE OF ASPHALT (FLEXIBLE) VERSUS CONCRETE (RIGID) PAVEMENT
It would be my great pleasure to clarify the misunderstanding of the Ministry’s new policy direction regarding the use of Rigid pavement on her projects. I have to state categorically that no Contractor is prevented from executing the scope works originally signed with the client once certain conditions are observed, which are provision of a 15year shelf-life Insurance Guarantee for the works and a maximum of 5% of Variation of Price (VoP) in the Contract. The Ministry’s new policy is to prevent excessive augmentation of contracts considering the scarcity of Forex and weakening of the Naira against the Dollar which makes the cost of bitumen (which is fully imported) increase in geometric progression against the arithmetic progression rise in cement prices in concrete road pavements. In these times of rising inflation and scarce resources, the Country needs to look inwards to conserve foreign exchange.

 

15.0 COMMENDATIONS
We thank the President and Commander-in-Chief of the Federal Republic of Nigeria, His Excellency, Senator Asiwaju Bola Ahmed Tinubu, GCFR for the intervention of his Renewed Hope administration in the Works sub-sector and approval of an enhanced budget envelop for the Federal Ministry of Works. We also thank the leadership of National Assembly, the Chairmen and members of the Works Committees and indeed members of the National Assembly for their painstakingness in ensuring the speedy passage of the 2024 Appropriation Bill.


Nweze David Umahi
Federal Ministry of Works
December, 2023

PHOTO NEWS

Mar
07
2024

HONOURABLE MINISTER OF WORKS, HIS EXCELLENCY SEN. ENGR. NWEZE DAVID UMAHI, CON, WITH OTHER DIGNITARIES DURING THE OFFICIAL HANDOVER OF THE FIRST PHASE OF THE PROJECT, MADE UP OF 47.47 KILOMETERS DUAL CARRIAGEWAY, TO HITECH CONSTRUCTION COMPANY LTD

Honourable Minister of Works, His Excellency Sen. Engr. Nweze David Umahi, CON, with other dignitaries during the official handover of the first phase of the project, made up of 47.47 kilometers dual carriageway, to Hitech Construction Company Ltd

Click To View More Pictures

PHOTO NEWS

Mar
05
2024

HON. MINISTER OF WORKS, HIS EXCELLENCY SEN. ENGR NWEZE DAVID UMAHI CON (RIGHT) WITH THE DIRECTOR, INFRASTRUCTURE AND URBAN DEVELOPMENT, MIKE SALAWOU HELD AT THE OFFICE OF THE HONOURABLE MINISTER FEDERAL MINISTRY OF WORKS, THIS 5TH MARCH 2024.

Hon. Minister of Works, His Excellency Sen. Engr Nweze David Umahi CON (Right) with the Director, Infrastructure and Urban Development, Mike Salawou held at the office of the Honourable Minister Federal Ministry of Works, this 5th March 2024.

Click To View More Pictures