The Federal Executive Council (FEC) also on Wednesday approved the construction of the section 1 of the Ilorin-Omuaran-Kabba Road for N21 billion to link Kwara and Kogi states.
The Minister of Power, Works and Housing, Mr Babatunde Fashola, said that FEC also approved a N589 million consultancy for Environmental Impact Assessment on the 200 kilometre Olorunshogbo Transmission line.
Fashola said the projects were consistent with the programmes of the federal government to reduce travel time and improve power supply to parts of the country..
“The second approval was for consultancy services for professionals to conduct line-route studies, Environmental Social Impact Assessment and resettlement action plan as well as environmental social management plan.
“(It) is in order for us to access the Japanese International Cooperation Agency (JICA) loan to support the Transmission Company of Nigeria (TCN) to continue its transmission grid expansion programme.’’
The Minister said that the TCN projects cover the routes which the transmission line would pass through.
He added that the 200 kilometre line would enable TCN evacuate power from the Olorunshogbo power plant to industrial clusters in Ogun and parts of Lagos state.
In his briefing, the Minister of Agriculture, Chief Audu Ogbe, said that the committee set up on the rising cost of food prices has submitted an interim report to the Council.
According to him, the committee identified the causes of the rise in prices as high cost of transportation and illegal taxation by states and local governments on producers and transporters.
He said that the good thing was that there was no real shortage of food, adding that Nigerians were groaning under the pain of high prices.
He attributed the high cost of transportation to the complete reliance on roads for evacuation of produce coupled with high cost of diesel and difficulties of trucks to move to places at the old fares.
“So we considered the following alternatives using railway wagons on the current railway networks as we did before. When we moved cattle from the North West to Lagos by rail, we brought down the costs.
“We avoided the multiple taxation visited on transporters in this country by local governments, road blocks, most of them not very legal, along the high ways, which delay movement and cause damage to a lot of foods like tomatoes.
“We decided to work with the state governments and the police to reduce those delays and we are going to adapt what they have in Cote D’Ivioire where trucks carrying food are given labels.
“In fact in Cote D’Ivoire, they cannot be stopped for more than 10 minutes anywhere even if something serious has happened.
“The security agencies will follow them to the port or to their destinations and come back to investigate whatever happens.
“Finally, we shall be looking into our reserves , if the situation in the next few days persists, then we have to see what we can bring out to lower the prices. (This is) because another round of harvests would be coming up again by the end of March,"Audu Ogbe said.
The Minister said there was really no starvation in the country, adding that there was also a lot of pressure on Nigerian food from West, North and Central Africa.
“Our food production is very robust and we are doing pretty well,’’ he added.
THE HON. MINISTER OF WORKS, H.E. SEN. (ENGR.) NWEZE DAVID UMAHI, CON, FNSE, FNATE ENGAGES STAKEHOLDERS IN ONDO STATE ON THE 63-KILOMETRE ALIGNMENT OF THE LAGOS - CALABAR COASTAL HIGHWAY PASSING THROUGH THE STATE, THURSDAY, 31ST OCTOBER, 2024 IN AKURE.
1
HON. MINISTER OF WORKS, HIS EXCELLENCY SEN. ENGR NWEZE DAVID UMAHI CON (RIGHT) WITH THE DIRECTOR, INFRASTRUCTURE AND URBAN DEVELOPMENT, MIKE SALAWOU HELD AT THE OFFICE OF THE HONOURABLE MINISTER FEDERAL MINISTRY OF WORKS, THIS 5TH MARCH 2024.
Hon. Minister of Works, His Excellency Sen. Engr Nweze David Umahi CON (Right) with the Director, Infrastructure and Urban Development, Mike Salawou held at the office of the Honourable Minister Federal Ministry of Works, this 5th March 2024.